Renovation Update - Lindsay Recreation Complex

March 28, 2011 - Work continued this week on the major renovation project at the Lindsay Recreation Complex.

Physical changes to the facility since the last communiqué include:

Washrooms

Finish mirror and access panel installation

Concessions

T-Bar ceilings and floor installed

Millwork installation starting

Corridor at Elevator

Commence drywall ceiling

Fitness Addition

Final ductwork revisions and duct insulation completed

T-Bar ceiling installed on both floors

Drywall in stairwell and corridor on going

Paint first and second floor drywall finishes

Administration Addition

Parapet framing

Aluminum windows installed

Family B/F Change Room / Shower / Washroom

Ductwork modifications completed

Drywall duct chase and ceiling repairs completed

T-Bar ceiling installed

Floor preparation completed and floor and wall tile started

Plans for the upcoming two weeks include:

Concessions

Millwork installation completed

Final painting

Cove base and ceiling tile installed

Mechanical and electrical finishes completed

Corridor 142 (main floor elevator)

Drywall ceilings and bulkheads completed

Millwork installed

Final painting

Elevator Lobby on 2nd Floor

Drywall taping completed

Painting new walls and bulkheads

Install display case, flooring, base and ceiling

Mechanical and electrical finishes

Elevator

Install dedicated phone line

Complete all outstanding items for final inspection

Lobby

Continue work on bulkheads

Pool Area

Install aluminum doors (delay due to hardware)

Complete floor tile at east window (delay due to hardware)

Install balance of exterior siding (delay due to hardware)

Paint balance of block and drywall bulkheads (delay due to hardware)

Fitness Addition

Drywall touch ups and taping on both floors and in stairwell to be completed

T-Bar ceilings and millwork installed

Painting finished

Commence flooring, mechanical and electrical finishes

Administration Addition

Louvers re-ducted

Roof parapets completed, low roof drain, roofing on low roof section

Install exterior doors and frame

Completed window frames and glazing to Lobby

Install masonry veneer

Underground plumbing rough-in to start

Prepare subgrade for slab on grade pour

Family B/F Change Room / Shower / Washroom

Tile and flooring, millwork, painting, plumbing and lighting completed

Toilet partitions, accessories and ceiling tiles installed

Final clean up

Deficiency inspection

Current Service Interruptions:

Hoarding at rear of Community Room and in main lobby

Relocation of all land based Fitness classes to the Victoria Park Armoury

Relocation of ramp to main entry

Elevator Access to Community Room unavailable

Closure of controlled-entry door to pool lobby

Detour in place for access to the Community Room.

Throughout construction regular updates will be available for our patrons and the public via our website (www.city.kawathalakes.on.ca/renovations)  and with information available within the facility. We ask your cooperation and understanding as our spaces are re-worked.

-30-

Media Inquiries:

Communications Officer

705-324-9411 extl 1355

communications@city.kawarthalakes.on.ca