Russell Street watermain replacement is underway in Lindsay

June 22, 2016 - Crews began work replacing the watermain on Russell Street in Lindsay on June 20.

The scope of this project includes the installation of a new watermain, water system, and asphalt that will improve both the underground road structure, and the surface of the road.

In order to accommodate construction Russell Street will be closed from Albert Street to Victoria Avenue commencing July 4, 2016.  Local residents and emergency vehicles will have access.  Residents can use Kent Street West and Glenelg Street West to bypass construction. This project is expected to be completed by September 30, 2016.

- 30 -

For more information about this project please contact:

Corby Purdy
Supervisor of Infrastructure, Design and Construction
705-324-9411 Extension 1155