Lindsay Recreation Complex Renovations
Latest News
December 5, 2011
August 29, 2011
August 11, 2011
July 26, 2011
May 31, 2011
April 15, 2011
March 28, 2011
February 22, 2011
We are pleased to announce the barrier free/family change room and the new two storey Fitness Centre are now open!
Construction to the main entrance is ongoing and detours are in place.
Physical changes to the facility since the last communiqué include:
Washrooms
Turnover
Concessions
Millwork complete
Awaiting counters
Corridor 142 (main floor elevator)
Drywall ceilings and bulkheads completed
Millwork installed
Elevator Lobby on 2nd Floor
Drywall taping, sanding and painting completed
Install display case, flooring, base and ceiling
Mechanical and electrical finishes
Elevator
Awaiting final inspection
Lobby
Continue work on bulkheads
Demolition of washrooms and interior walls
Pool Area
Aluminum doors installed
Complete tile under windows
Complete exterior siding
Fitness Addition
Drywall ongoing in Fitness Studio
Administration Addition
Mechanical and electrical rough in ongoing
Studs and drywall complete
Family B/F Change Room / Shower / Washroom
Complete
Entrance Addition
Footings and foundation complete
Backfill complete
Plans for the upcoming two weeks include:
Washrooms
Final clean up and turn over
Concessions
Counter, plumbing fixture and trims
Corridor 142
Electrical fixtures and turnover
Elevator Lobby on 2nd Floor
Final clean up and turn over
Elevator
Final inspection clean up and turn over
Lobby 102
Drywall bulkheads from Elevator to Aquatics Door ongoing
Mechanical and electrical rough in
Sprinkler installation ongoing
Pool Area
Paint balance of block and drywall bulkheads
Fitness Addition including Corridor 118 and Lobby 112
Stair 6 remains closed – detour in place
Administration Addition
Mechanical /electrical ongoing
Entrance Addition
Exterior steel to commence
Current Service Interruptions:
Main entry closed to the public – detours in place
Main lobby and Community Room closed to the public until main entry re-opens.
Relocation of main office to Pool lobby
Relocation of all land based Fitness classes to the Victoria Park Armoury
Throughout construction regular updates will be available for our patrons and the public via our website (www.city.kawathalakes.on.caa/renovations) and with information available within the facility. We ask your cooperation and understanding as our spaces are re-worked.